Customer Case Study:

Barwon Water Blackrock Treatment Plant Solar Farm

Scope of works

Design and construction of a 2MW solar PV system, integration with on site Supervisory control and data acquisition (SCADA). This project is an extension of stage 1, which included 1MW solar PV system and a purpose built power factor correction, specialised Static Var Generator system (SVG), remote energy monitoring and revenue grade metering.

Key Results from stage 1

  • Custom built inverter enclosure that is designed and engineered for the extremely corrisove coastal environment.
  • Successful installation of Static Var Generator system to correct power factor corrections on the high voltage side of the treatment plant.
  • String level monitoring of solar panels.
    No disruption to treatment plant operations throughout the 5 month construction program.

Fast Facts

  • Location

    Connewarre VIC 3227
  • Date of completion

    Est. June 2019
  • Yearly energy usage

    3019 MWh
  • System size

    2MW solar
  • CO2 Emissions saved

    1500 tonnes per year
  • Panels

    5544 x 365/370w Trina Panels
  • Inverters

    32 x 60kW SMA
  • Railing

    S-rack