Customer Case Study:

Barwon Water 1MW Solar Farm with Power Factor Correction

Barwon Water

Design, supply and construction of a 1MW ground mounted solar farm with power factor correction equipment.

Commissioning expected early December 2017.

Key Components:

  • 2880 x Trina 350w frameless panels
  • 6 x SMA 60kW inverters in a purpose built inverter kiosk station
  • 1MVA, 3-phase, integrated RMU transformer and enclosure
  • 1.4km underground HV cable run