FGB Kurraca Microgrid
800kWh BESS
800kVA generators
Design and construction of a full off-grid hybrid renewable energy system integrating solar PV, BESS and diesel generators.
Key outcomes
- The integrated microgrid solution enabled FGB to have a fully operational facility within one year, avoiding a more costly grid connection that would have delayed operations by a further two years, with solar and BESS forming the majority of facility supply and generators retained as backup to minimise ongoing fuel costs.
- A ComAp integrated control solution was deployed, with all control wiring completed in-house by the generator supplier to reduce on-site installation costs and programme risk.
- Development approval was secured prior to design commencement, accounting for a 120m cultural heritage easement off an existing creek, with DA works completed in parallel with design to maintain programme.
- A modular BESS configuration was selected for cost and programme efficiency, with careful consideration given to the additional control complexity of managing multiple units in tandem compared to a single containerised solution.